Forum Discussion
NickC_2021
Jun 18, 2021Copper Contributor
Using MS Project in SharePoint
I am creating a program schedule that consists of a Consolidated Microsoft Project schedule (an Integrated Master Schedule and 3 sub-project schedules). We are using Project Professional 2019. My t...
Jun 18, 2021
Nick -- You could save Read-Only COPIES of each project in the SharePoint site, but (and this is a big BUT), each of your team members would either need their own licensed copy of Microsoft Project, or they would need a licensed copy of a Microsoft Project viewer. There are a number of project viewers available for purchase, such as the one from Steelray, but there are no free project viewers (at least none that I am aware of). Hope this helps.
NickC_2021
Jun 19, 2021Copper Contributor
Thanks for the clarification Dale.