Using MS Project in SharePoint
I am creating a program schedule that consists of a Consolidated Microsoft Project schedule (an Integrated Master Schedule and 3 sub-project schedules). We are using Project Professional 2019. My t...
Jun 18, 2021
Nick -- The master project feature in Microsoft Project does not work if the master project and the subprojects are saved in SharePoint. You will need to save your master project and all of its subprojects in a network drive to which all of your PMs have Read/Write access. Hope this helps.
- NickC_2021Jun 18, 2021Copper Contributor
Thanks Dale. Would it be possible for team members to view the files in SharePoint. Perhaps saving the files as Read-only in SharePoint and then instructing anyone who wants to see the schedules that they must download as a SET to view?
- Jun 18, 2021Nick -- You could save Read-Only COPIES of each project in the SharePoint site, but (and this is a big BUT), each of your team members would either need their own licensed copy of Microsoft Project, or they would need a licensed copy of a Microsoft Project viewer. There are a number of project viewers available for purchase, such as the one from Steelray, but there are no free project viewers (at least none that I am aware of). Hope this helps.
- NickC_2021Jun 19, 2021Copper ContributorThanks for the clarification Dale.