Forum Discussion
Matt_DeCecco
Apr 19, 2024Copper Contributor
Using Microsoft Project for the Web Built in Power Apps. New Project not adding Calendar id.
Hopefully my post is in the correct category. Tried posting this to Power Apps. I am using Project for the Web I am using the Microsoft Project Power Apps Model Driven App and have customize...
RodFromm
Apr 19, 2024Iron Contributor
Matt_DeCecco - Verify your default Work Hour Template is still set and the template is not corrupted. We actually unlocked the Calendar template filed to allow PMs to assign different calendar and we added the Schedule Mode field, above the Calendar template field, to allow them to tailor the mode to the project.
- Project Accelerator is opened.
- Click Projects in the bottom left corner of the page then select Settings
- Under General, select Parameters
- Select the Default Organization Unit (there should only be one) then click Edit at the top of page.
- On the Parameters page, set/review your Work Hour Template