Using logic to drive task column values

Good afternoon,   I have a column which is set to a binary state, Active/Inactive as Text 2 (named Status, which is different than the Project Status field).  I also have Tasks with two indented su...
  • John-project's avatar
    John-project
    Aug 27, 2023

    Gordon_Smith 

    How about a simpler approach. You mentioned you want a quick-look filtered view. How about a simple custom filter. Here's a sample plan with [performance]task status (Text2) selected via the dropdown.

    Now here's a filter for active tasks with the option to show related summary levels

    Applying the filter gives this

    Does that do what you need?

     

    Buuuuuut, if that doesn't quite do everything you need, here is the macro code to implement all your criteria, at least if I understand it correctly.

    John