Using enterprise custom fields

Hello

I created an enterprise resource field called Limit_hours as shown below where I could enter max hours a resource could work.

When I try to edit the resource in pwa, I am able to add a value which is saved

 

But I am not able to i. Add this field as a column in resource centre.

ii. Add this field as a column in resource sheet in project professional.

 

Please advise on why this is happening.

Thanks

 

 

 

  • Lakshmisv --

    Delete this field and recreate it as a custom Number field and let us know the result.

2 Replies

  • Lakshmisv --

    Delete this field and recreate it as a custom Number field and let us know the result.
    • Lakshmisv's avatar
      Lakshmisv
      Tin Contributor

      Dale_HowardMVPThanks for your reply.

      Surprisingly both things work today with no changes made from my side.

      Looks like it needed a time gap to sync with the server!