Forum Discussion
ZsofiH
Oct 18, 2023Copper Contributor
Using advanced dependencies in enterprise project types - web version
Hi Team, Is there a way to use the advanced task dependencies function in Project for web/ Enterprise projects? In the desktop version I could find a way to change the linking type from the default...
ZsofiH
Oct 19, 2023Copper Contributor
Hi Dale, Thank you for your reply!
I am afraid using Enterprise project types in the web version doesn't offer you these columns. Predecessors field can be added only to any kind of view.
I could not find the function where I can set what kind of dependency I would like to use. The only option is the default.
I am afraid using Enterprise project types in the web version doesn't offer you these columns. Predecessors field can be added only to any kind of view.
I could not find the function where I can set what kind of dependency I would like to use. The only option is the default.
Oct 19, 2023
ZsofiH --
Now I'm really confused. Are you using Project for the Web (project.microsoft.com) or are you using Project Online (companyname.sharepoint.com/sites/pwa)? The reason I ask is because in Project for the Web, there is no Predecessors or Successors columns. There are the Dependents (after) and Depends On columns. Please let me know and we will try to help you.
Now I'm really confused. Are you using Project for the Web (project.microsoft.com) or are you using Project Online (companyname.sharepoint.com/sites/pwa)? The reason I ask is because in Project for the Web, there is no Predecessors or Successors columns. There are the Dependents (after) and Depends On columns. Please let me know and we will try to help you.
- ZsofiHOct 20, 2023Copper ContributorYou are right Dale, I got confused by the phrases. Si I use Project Online - web version and I have the desktop version installed too.
- Oct 19, 2023ZsofiH --
Also, I forgot to mention that in Project for the Web, there is no concept of Enterprise Project Types. But in Project Online, Enterprise Project Types are an option that can be configured for different types of projects that are managed with Project Online.