User tasks from all projects in one page
Hi, Is it possible to create a power app to view all user's tasks (from all organization teams projects where he is assigned) in one page? It would be ideal to see a schedule graph with the begin/en...
- Aug 02, 2024If you are using Project for the web in a non-default environment then yes. You simply need to create a view to do this.
RodFromm
Aug 01, 2024Steel Contributor
asta1109 - I don't know what your requirements are, but you don't need a PowerApp to do what your talking about. This can be done with Power BI and you'll need access to all the projects. If the projects are in the default environment this is pretty simple, but if it is across multiple named instances (Project Accelerator) it can be done, but take a little more effort setting it up Power Query to make it happen.