Use Save for Sharing for Colleagues who Don't have Project Pro?

You need Project Professional to open schedules from Project Server and publish updates/changes. We have individuals in our organization who only have Project Standard, but need to provide input into...
  • Dale_HowardMVP's avatar
    Oct 31, 2025

    Good question.  When Microsoft introduced this feature, it was meant to do exactly what you want to do.  At the time, I found that people receiving the shared file MUST HAVE the same version of Microsoft Project as is currently used with Project Online or Project Server.  The MPP file that is generated will contain all of the custom enterprise objects from your Project Server system, however, the people using Microsoft Project Standard will NOT be able to see those enterprise objects, nor will the objects be lost in the round trip process.  Before you proceed with implementing this with all Microsoft Project Standard users, I would recommend that you run multiple tests with one or two users to make sure that the process actually works, and does not damage or corrupted the shared enterprise project.  Hope this helps.