Uploading/Data Mapping Recurring Task Information for MS Project
I would like to upload a number of recurring tasks into MS Project. How/where do I find the field names associated with recurring tasks? For example: recurring pattern, number of occurrences, etc. ...
Jeff_Hebert
Jan 25, 2023Copper Contributor
Hello John, I'm using MS Project Professional Online Desktop. I have an MS Access Database of Equipment and associated tasks (recurring preventative maintenance requirements). From Access I can generate a list of tasks with the necessary fields as a table to export that I could then upload to Project. I have Task Name, Duration, Resource information, etc., and I have how often the task needs to recure (daily, weekly, monthly, etc.). I want to use project to estimate resource loading for maintenance over a multi year timeframe. I assume there must be defined field names in project that would accept the data needed to generate the recurring tasks. Does this make sense?
John-project
Jan 25, 2023Silver Contributor
Jeff_Herbert,
Yes, it does make sense.
I haven't worked with an import from Access for several years, it was done using SQL. However, unless there is some avenue through the Project database tables, Project can only import basic fields such as Task Name, Duration, and Resource information. There is no way to directly import recurrence information but it could be done with VBA.
John
Yes, it does make sense.
I haven't worked with an import from Access for several years, it was done using SQL. However, unless there is some avenue through the Project database tables, Project can only import basic fields such as Task Name, Duration, and Resource information. There is no way to directly import recurrence information but it could be done with VBA.
John
- Jeff_HebertJan 25, 2023Copper ContributorWhen I go through the Upload Wizard in Project there is an opportunity to map the fields in the upload file (excel spreadsheet) to the fields in project. The Project Field list is available in the pull down (it is the same list as the list in the Add New Column" in the Gantt Chart View and the "Recurring" field is available (I can set this to yes for recurring, what I don't see are the fields that would be associated with the Frequency. They must exist in the project file as they can be set in the recurring task window, but apparently they are not exposed for mapping. If anyone knows how this can be done using VBA that would be interesting.
- John-projectJan 26, 2023Silver ContributorJeff_Herbert,
As a follow-up to Dal's input, if your import is a one time action to produce a maintenance plan in Project then the best approach is to manually create the recurring tasks. If the import is something that will be done on a regular basis (e.g. monthly) then the VBA approach is better.
And as I thought about it more, there is noting magic about a recurring task. It's nothing more than a summary line with subtasks "packaged" in a format process for creating the subtasks. Creating a summary line with multiple periodic subtasks is very doable with VBA.
John- Jeff_HebertJan 26, 2023Copper ContributorThanks Dal and John, This process would need to be done more than once as this is for different scenario planning. I actually have 1000s of these repeating tasks in the database, with varying frequencies for weekly to every 5,10,15,years etc. So the manual option would not be possible. If I want to look at a ten year plan I will need to populate all of the tasks for a ten tear period. I think I will need to generate each recurrence of the task as part of a report out of Access and then just load the prescheduled tasks into Project. It is an interesting challenge and I'm still building the database of tasks. I suspect the VBA option would be pretty complicated given the volume of tasks that need to be loaded. I need to maintain the base tasks in a db for a number of other reasons. Thanks for you input, it is much appreciated.
- John-projectJan 25, 2023Silver Contributor
Jeff_Herbert,
Yes the Recurring field can be imported but it will come in as a single task (i.e. yes or no will import as no in the Recurring field.
I'm going to have to back-peddle on the VBA idea. After posting, I took a quick look at Project's object model and unfortunately details associated with a recurring task are not available. Sorry for the misstep. But, not to be totally thwarted, VBA could be used to emulate a recurring task's individual elements given a "flag" in the Excel data that initiates the process. It's called "thinking outside the bun".
John