Forum Discussion

Peter_Eng's avatar
Peter_Eng
Copper Contributor
Oct 26, 2021
Solved

Updating task progress for resources without PC access

Hi All, I'm using a MS Project Online to manage program of works. In this case, we have a large team of people, many of whom don't have access to computers. These can like electricians, mechanical f...
  • Dale_HowardMVP's avatar
    Oct 27, 2021
    Peter_Eng --

    Excellent question, my friend! Here is how you should handle this situation, using the scenario you describe of the plant shutdown:

    1. In the Microsoft Project schedule, add the Supervisor as a project team member using the Build Team dialog.
    2. Leave the tasks in question assigned to the Labor resources.
    3. Apply the Resource Usage view.
    4. In the Resource Usage view, insert the Assignment Owner column to the right of the Resource Name column.
    5. In the Assignment Owner column, you will see the names of the Labor resources for the tasks to which they are assigned. Change the Assignment Owner value from the name of the Labor resources to the name of the Supervisor for each of these tasks.
    6. Save and publish the project.
    7. Ask your application administrator to add both the Status Manager and Resource Name columns to the My Assignments view.

    By completing the preceding steps, the Supervisor will now be able to see the tasks on his/her Tasks page that are assigned to the Labor resources. The Resource Name column will help the Supervisor to determine which tasks are assigned to which of the Labor resources. Hope this helps.