Forum Discussion

NKumar2010's avatar
NKumar2010
Brass Contributor
Jun 03, 2022
Solved

Updating Baseline Finish Dates in MS Project

Hi,    I have created a schedule and created the 1st baseline ("Baseline Finish" column) based on an overall program plan.  The task tracking has begun and Finish column now shows the forecasted fin...
  • John-project's avatar
    Jun 03, 2022
    NKumar2010,
    The simple answer is, manually update the Baseline Finish field. Baseline fields are static, that is, they are fields Project uses to transfer (copy) dynamic field data for a snapshot of a plan's original metrics. Since they are static fields, they are directly editable by the user.

    However, even though I answered your question, I can't help but wonder who told you a "lot of dates" were incorrect and what is the basis for the "new" dates. Are they saying all the start dates are okay? That doesn't make sense. And if baseline finish dates need to be altered, what about baseline duration, or baseline cost?

    If the original plan was indeed questionable but work has already started, I think the best plan of action is to set a new baseline, perhaps using the Baseline1 fields from this point on. If you try to tweak the original baseline (i.e. manual entry in Baseline Finish field), from my viewpoint the "corrected" baseline will be corrupt (i.e. not valid for anything).

    John

Resources