Forum Discussion
JeremySRITS
Mar 04, 2019Brass Contributor
Understanding Project SharePoint Integration
We use Office 365 with SharePoint Online. No on-prem SharePoint whatsoever. I am trying to understand how Project Online is integrated with SharePoint. Where exactly are the "projects" created with P...
- Mar 08, 2019
Hello,
Project Online is a feature built in SharePoint Online, Project Online consists of 2 features for end users to interact with the data, Project Online Desktop and Project Web App (PWA). Project Online Desktop works with Project Online and is the desktop tool for creating and editing projects. PWA is the web interface for Project Online that also enables users to create / edit projects etc., this is the SharePoint site collection. It's a special SharePoint Online site collection that whilst it is SharePoint it has it's own access model. There are two options, the default SharePoint permission mode or the Project permission mode. Here is a really quick getting started guide: https://docs.microsoft.com/en-us/projectonline/get-started-with-project-online
Data created in Project Online such as Projects are stored in the Project Online tables inside the SharePoint Online content database.
Hope that helps
Paul
Paul_Mather
Mar 14, 2019MVP
Hello,
Yes, the PWA admin (or users that have access to the project) can either check this is in PWA or Project Online Desktop client.
- In PWA, access the Project Center, select the project row, then on the Projects tab click "Build Team". On the right hand side of the grid it will show you the resources that are on the Project Team
- In Project Online Desktop Client, open the project then Press Ctrl+T (short cut for build team), then on the right hand side of the pop up you will see the Project Resources
Repeat for each project you need to check.
Paul
JeremySRITS
Mar 14, 2019Brass Contributor
Paul,
Thanks for all your responses. This has been helpful to me!