Unable to See Resources in Resource Center
I am setting up a new PWA. I have been given full Admin rights. I cannot see resources in the Resource Center. I have successfully added our Active Directory as well as manually creating resources...
- Apr 19, 2022Paul and Dale, I did some more searching and found a support article from 2018 that turned out to be unrelated but gave me an idea. I logged in using Edge instead of Chrome and can see the Resource table. Oddly, everything else works well in Chrome. Thank you again for taking the time to answer my question.
Paul_Mather
Apr 12, 2022MVP
Hello Matt_Mandry ,
So you can access the resource center but you can see any resources, just an empty grid? Are you using the Project Permission mode or SharePoint Permission mode?
Paul