Unable to Establish PWA Connection
I have created and successfully shared our PWA with a colleague. I am trying to share it with two more colleagues who have the same MS Project subscription as we do. I have granted them access to t...
- Oct 17, 2022Matt_M --
I would recommend that you change your Project Online instance to Project Permissions Mode. Then add your users to the Project Managers security group if they only need to manage projects, or to the Administrators group if they need to administer the environment. Hope this helps.
Matt__M
Oct 17, 2022Copper Contributor
Thank you very much Dale! I was in Project Permissions Mode. I had not added them (or the original colleague) to the PM group. They have successfully connected.
Oct 17, 2022
Matt_M --
Excellent. Thanks for letting me know of your success. Way to go, my friend! 🙂