Solved

Unable to Establish PWA Connection

I have created and successfully shared our PWA with a colleague.  I am trying to share it with two more colleagues who have the same MS Project subscription as we do.  I have granted them access to t...
  • Dale_HowardMVP's avatar
    Oct 17, 2022
    Matt_M --

    I would recommend that you change your Project Online instance to Project Permissions Mode. Then add your users to the Project Managers security group if they only need to manage projects, or to the Administrators group if they need to administer the environment. Hope this helps.