Forum Discussion

BrunoRB's avatar
BrunoRB
Copper Contributor
Jul 14, 2022
Solved

Two resources changing their base calendar simultaneously

Hi, I'm using Project Professional 2019. I've created some base calendar for all the projects that I have.  I have two resources that when I change the base calendar of one of them, the othe...
  • Simkonis's avatar
    Simkonis
    Oct 04, 2024
    Thanks a lot. This last instruction helped me to resolve exactly the same issue I had.