Transfer Gantt Chart to PowerPoint
Good morning! How do I transfer a Gantt chart created in MS Project to PowerPoint? Is this something that can be done at all? Thank you, Karine
- Sep 16, 2022Karine0918 --
Yes, this can be done, but the method for doing this involves capturing a screenshot of the Gantt Chart view. Microsoft Project has its own tool for doing this. Display the Gantt Chart view, expose the column you want to show, and set the level of zoom as desired for the Gantt Chart screen.
In the Clipboard section of the Task ribbon, click the Copy pick list button (the little dropdown arrow on the Copy button) and select the Copy Picture item. In the Copy Picture dialog, you will probably want to experiment with the settings in the three sections of the dialog. The first two options in the Render Image section will copy a screenshot to the Windows Clipboard, from which you can paste the image to PowerPoint. Hope this helps.
Sep 16, 2022
Karine0918 --
Yes, this can be done, but the method for doing this involves capturing a screenshot of the Gantt Chart view. Microsoft Project has its own tool for doing this. Display the Gantt Chart view, expose the column you want to show, and set the level of zoom as desired for the Gantt Chart screen.
In the Clipboard section of the Task ribbon, click the Copy pick list button (the little dropdown arrow on the Copy button) and select the Copy Picture item. In the Copy Picture dialog, you will probably want to experiment with the settings in the three sections of the dialog. The first two options in the Render Image section will copy a screenshot to the Windows Clipboard, from which you can paste the image to PowerPoint. Hope this helps.
Yes, this can be done, but the method for doing this involves capturing a screenshot of the Gantt Chart view. Microsoft Project has its own tool for doing this. Display the Gantt Chart view, expose the column you want to show, and set the level of zoom as desired for the Gantt Chart screen.
In the Clipboard section of the Task ribbon, click the Copy pick list button (the little dropdown arrow on the Copy button) and select the Copy Picture item. In the Copy Picture dialog, you will probably want to experiment with the settings in the three sections of the dialog. The first two options in the Render Image section will copy a screenshot to the Windows Clipboard, from which you can paste the image to PowerPoint. Hope this helps.
Karine0918
Sep 22, 2022Copper Contributor
Thank you! That seems easy enough to do. 🙂