Forum Discussion

shawman60's avatar
shawman60
Copper Contributor
Jun 02, 2023

Tracking unit progress on ms project

I am trying to figure out how to get MSP to measure my work correctly. Example: I have 10 days to install 10,000 feet of cable. On day one I install 2500 feet and put my progress in as 25%. The probl...
  • John-project's avatar
    Jun 03, 2023

    shawman60 

    Sorry but that's not how the progress line on the Gantt bar works. Percent complete is a duration based parameter so if you enter 25% for a 10 day task, Project will show 2.5 days of progress. Agreed, not a very useful metric.

     

    Here's what you can do. Show the Actual Duration field and the Physical % Complete fields, hide the Percent Complete field. Then you can enter the number of days and whatever percentage of work you feel is complete.

    Hope this helps.

    John

Resources