Forum Discussion
Tracking unit progress on ms project
- Jun 03, 2023
Sorry but that's not how the progress line on the Gantt bar works. Percent complete is a duration based parameter so if you enter 25% for a 10 day task, Project will show 2.5 days of progress. Agreed, not a very useful metric.
Here's what you can do. Show the Actual Duration field and the Physical % Complete fields, hide the Percent Complete field. Then you can enter the number of days and whatever percentage of work you feel is complete.
Hope this helps.
John
Sorry but that's not how the progress line on the Gantt bar works. Percent complete is a duration based parameter so if you enter 25% for a 10 day task, Project will show 2.5 days of progress. Agreed, not a very useful metric.
Here's what you can do. Show the Actual Duration field and the Physical % Complete fields, hide the Percent Complete field. Then you can enter the number of days and whatever percentage of work you feel is complete.
Hope this helps.
John
- shawman60Jun 05, 2023Copper Contributor
I will make that work and assign physical % complete to my task bars on gantt chart - Thanks for your help John-project
- John-projectJun 05, 2023Silver Contributorshawman60,
You're welcome and thanks for the feedback.
John