Forum Discussion
saintbm08
Feb 01, 2024Copper Contributor
Tracking Man Hours
I'm working on tracking man hours associated to a project. Question 1: Is there a way Project will calculate man hours based on the resource "work" as it relates to the duration of the task? F...
John-project
Feb 01, 2024Silver Contributor
Yes, and yes.
Question 1:
This screen shot shows a 10 day fixed duration task with two individual resources assigned at 100%.
Question 2:
That same task is now statused at 50% complete. The Remaining Work field shows 80 hours
Hope this helps.
John