Forum Discussion
ndrogo-
Jun 13, 2023Tin Contributor
Tracking Date Changes
Does anyone have any way to track and report when a project for the web tasks date gets changed. I have no way to show if tasks dates keep moving out. Any suggestions would be great. I was thinki...
ndrogo-
Jun 17, 2023Tin Contributor
Anyone have a solution for above?
Jun 17, 2023
ndrogo --
As it currently exists, the feature you want is not available in Project for the Web. However, Microsoft just announced that auditing will be added to the tool, which will give you the information you seek. Refer to the following:
https://techcommunity.microsoft.com/t5/project-blog/auditing-capabilities-coming-to-microsoft-project-microsoft/ba-p/3841229
Hope this helps.
As it currently exists, the feature you want is not available in Project for the Web. However, Microsoft just announced that auditing will be added to the tool, which will give you the information you seek. Refer to the following:
https://techcommunity.microsoft.com/t5/project-blog/auditing-capabilities-coming-to-microsoft-project-microsoft/ba-p/3841229
Hope this helps.
- ndrogo-Jun 19, 2023Tin Contributor
Dale_HowardMVP I turned this on and searched but got no results.