Forum Discussion
dc_27
Sep 12, 2022Copper Contributor
Trace Logic - How to easily see a milestone's predecessors
P6 user question again, wondering how i can replicate this functionality from P6 in MS Project In P6 i can click on a milestone (or any activity) and see it's predecessors visually to find ...
dc_27
Sep 13, 2022Copper Contributor
Getting there!
Can we customise the relationship diagram to show driving logic / dates / critical relationships? Otherwise, i'm still scrolling around to find the useful info
David
Can we customise the relationship diagram to show driving logic / dates / critical relationships? Otherwise, i'm still scrolling around to find the useful info
David
ineeju
Sep 13, 2022Copper Contributor
1. Display only all predecessors and all successors of the selected task using filters or macros.(★)
2. Change the relationship diagram view to the network diagram view.
3. Select all filtered tasks in the Gantt chart. (★)
4. It looks like P6 in the network diagram.
5. The relationship diagram shows only direct predecessors and successors of the selected task, and the network diagram shows all predecessors and all successors of the selected task.
p.s.
Unfortunately, I saw it somewhere 4 years ago and did all the tests, but now I can't even find the test file, and I can't remember where I saw it.