Forum Discussion

Jmorganh's avatar
Jmorganh
Copper Contributor
Jul 15, 2022

totaling equipment usage

We want to use Project to track the daily usage of equipment.

using this total to know if we have enough equipment each day.

 

how can this be totaled and displayed

 

thanks

 

5 Replies

  • John-project's avatar
    John-project
    Silver Contributor
    jmorganh,
    This sounds like something better suited for Excel, not Project. Why do you think you want to use Project?

    If you do want to or are already using Project, are the various pieces of equipment set up a work type resources and is each piece assigned to a specific task?

    We need more definitive information about what you are trying to do before we can offer meaningful help.
    John
    • Jmorganh's avatar
      Jmorganh
      Copper Contributor

      John-project 

      We are starting to use Project to track and show projects/jobs and how they overlap by dates.

      We also want to show how the qty of equipment is used by totals.

       There will be 20  to 50 jobs going on at once. Some are a few days, some go for months.

      Looking to monitor how many trucks, trailers, and flagger personnel are needed by day.  This will allow us to know when we will be overbooked or need to get more equipment or hire more personnel.

       

      What do you think is best tool to track this?

      Thank you for your opinion.

      • John-project's avatar
        John-project
        Silver Contributor
        Jmorganh,
        Project does not tell you how many resources you need, rather, you tell Project how many resources (e.g. people & equipment) are available and you assign those resources to various tasks. Project will tell you if any of those resources are overallocated, (i.e. using more of a given resource than is available over a specific time), and by how much. In that regard project will tell you how much any of those resources are "overbooked" and you can take action to get more resources or perhaps re-shuffle the work load to use the resources you have. Project's leveling functionality can help with that.

        Over any given time period (e.g minute, hour, day, etc.) Project can tell you how many of each type of resource is being used, so in that regard Project will show the quantity of equipment used.

        So if you set your plan up correctly Project will tell you how many resources are being used and if overbooked, tell you by how much.

        Hope this helps.
        John

Resources