Forum Discussion

MiguelMarques's avatar
MiguelMarques
Copper Contributor
Sep 01, 2023
Solved

Total total peak units per task

Hi Everyone,   I´ve searched everywhere and i can't still figure out how to show the total peak unit per tasks and/or summary task?   For example, if I've got a task with 2 resources I would ...
  • John-project's avatar
    Sep 01, 2023
    Migeul Marques,
    Sorry but the only way I can see to get what you want is to export Project data to Excel and then create the total values in a custom report. There is no way to do it directly in Project.
    John