Total Project Progress % Report & S-Curve Report (E, P, C, C) - MS Project 2019 (Desktop)
Hi All, This thread is a two part question. The Schedule does not contain any resources, this is purely task driven (Dates & Duration). The client is essentially looking to establish what we had ...
John-project
Jun 07, 2024Silver Contributor
Wow, that's quite a pile of stuff you're after. Just curious, if the plan is only dates and duration, how do you determine the percent complete at any given time? Without some realistic metrics (e.g. work completed against work planned), it seems all very subjective.
But to address your metric items.
1. How exactly do you define cumulative late planned % (i.e. what does "late planned" even mean)?
2. The same for "this period late planned".
And yes, if you are doing duration based only progress (meaningless in my view), then "actual %" would be % Complete. But you'll have to define exactly what you mean by b, c, d & e. There are no such fields in Project.
John