Forum Discussion
Timesheet Single Entry Mode
Thank you for your suggestion. We already have this deselected. This only seems to impact the task within the project file at completeness levels under 100%. The issue we are having almost seems like a glitch or oversight from MS. The behavior isn't logical to me.
I've seen this before. At the resource assignment level, when the Actual Work for the assignment doesn't match the hours entered in a user's timesheet MS pre-populates the timesheet with Actuals. It distributes the Remaining Work over the duration and applies it to the current and future timesheet when they are opened.
To identify these issues, we created a Power BI report that compares the Assignment level Actual Work to Timesheet hours. When there is a difference just open the plan and update assignment level Actual Work to match Timesheet hours submitted.