Forum Discussion

danny_harris's avatar
danny_harris
Copper Contributor
Jun 12, 2023

Timesheet approval by project

Hi Community,

 

Is it possible to set up timesheet approvals so that the approver can be the project manager or the person timesheeting can select the appropriate approver for each row? 

 

My use case is: 

I have several projects that I need to timesheet my time against. 

 

I fill in my timesheets and want to submit them for approval to the project managers that are managing each of my projects to approve. 

 

Currently, I can only see that, as an enterprise resource, I can only have 1 approver that my timesheets go to for approval. 

 

Any help on my use case would be beneficial. 

 

Thanks,

Danny

9 Replies

  • Danny --

    In organizations that track task progress in Project Online using the Timesheet feature, there actually TWO types of approvals:

    1. The designated Timesheet Manager for each resource will need to approve the weekly timesheet for each resource that reports to him/her. This approval is done on the Approval Center page, and approval is applied to each user's entire timesheet.

    2. Regardless of whether timesheet are approved or not, the project manager of each project will see pending task updates for his/her team members on the Approval Center page of PWA. When the PM approves the pending task updates, the task progress will be entered automatically in the enterprise project associated with each set of pending task updates.

    In the two scenarios above, there is no way to designate the Timesheet Manager to also be the project manager unless they are already the same person. Does that help? Let us know.
    • NeeOk940's avatar
      NeeOk940
      Copper Contributor
      Hello Dale,
      Is it possible to add a new column to the Timesheet Approval History view?
      For example the date of approval? Right now I am seeing only these:
      Resource Name; Timesheet Name; Period; Status; Total; Actual Total; Overtime Total; Non-Billable Total; Non-Billable Overtime Total.
      • NeeOK940 --

        No, that is not possible. The Timesheet Approval History view is a built-in view that cannot be edited by either your Project Online app admin or by the user. Sorry, but hope this helps