Forum Discussion
kranis
Jul 18, 2020Copper Contributor
Timesheet app?
This site tells there is functionality for "Timesheet submission". https://www.microsoft.com/en-us/microsoft-365/project/compare-microsoft-project-management-software i´m trying to figure out if...
- Jul 18, 2020
Hello kranis ,
Yes there is an API for Timesheets: https://docs.microsoft.com/en-us/previous-versions/office/project-javascript-api/jj668309(v=office.15)
Paul
kranis
Jul 18, 2020Copper Contributor
Paul_MatherThanks for your reply!
Yes. I could build my app in Power Portal. That would be really cool. However, I need a way to fetch the title of each row, and also a way to push updates (how many completed hours for each row).
Hopefully MS project provides an REST api for this?
Paul_Mather
Jul 18, 2020MVP
Hello kranis ,
Yes there is an API for Timesheets: https://docs.microsoft.com/en-us/previous-versions/office/project-javascript-api/jj668309(v=office.15)
Paul
- Vygantas RaišysJan 25, 2022Copper Contributor
Is it still valid for Project Server 2016 andup? On the page it mentioned "Valid for Project Server 2013".