Forum Discussion
LisaJanssen
Mar 14, 2024Copper Contributor
Timeline
Hi, I am new to using Microsoft Project. I have combined 2 projects into a master file. I would like to create a timeline, but I need to add the summary name to task. Both my projects have ...
- Mar 14, 2024LisaJanssen,
This should do it. Run it at master level and then close the master. You will get a couple of messages asking if you want to save changes. Answer "yes" to the first message and "yes to all" on the second message.
John
Sub AddProjToSubsAtMstrLevel()
Dim t As Task
Dim sp As Subproject
For Each t In ActiveProject.Tasks
t.Name = t.Project & " - " & t.Name
Next t
End Sub
John-project
Mar 14, 2024Silver Contributor
Yes that can be done but you will have to physically add the Project designator to each task in each subproject. For example, in this master file with three inserted subprojects each subproject has a "task 2". A project designator is prefixed on each subproject task.
So what's the best way to add the prefix? Well, there are two methods. One is to manually type it in and the other is via a simple macro. If you're interested in the latter, I can provide that.
Hope this helps.
John
LisaJanssen
Mar 14, 2024Copper Contributor
John-project , Thanks John, yes I would also like to see the Macro
- John-projectMar 14, 2024Silver ContributorLisaJanssen,
This should do it. Run it at master level and then close the master. You will get a couple of messages asking if you want to save changes. Answer "yes" to the first message and "yes to all" on the second message.
John
Sub AddProjToSubsAtMstrLevel()
Dim t As Task
Dim sp As Subproject
For Each t In ActiveProject.Tasks
t.Name = t.Project & " - " & t.Name
Next t
End Sub- LisaJanssenMar 14, 2024Copper ContributorThanks for all the help John, it does not like this string
t.Name = t.Project & " - " & t.Name- John-projectMar 14, 2024Silver ContributorLisaJanssen,
Are you running the macro at master level?
When you get the error message, hit the "Debug button". Then hover you mouse over each of the arguments in the string. What do you see for each?
Could you post a screen shot of your master?
John