Forum Discussion

henrikstrand's avatar
henrikstrand
Copper Contributor
Nov 04, 2024

Timeline View, show amount of days insted of start and finish date?

In the timeline view, I would like to see the number of days each activity takes rather than the start and finish dates. How can I change that?

  • henrikstrand,

    Sorry but the timeline text is limited to 4 items: Task Dates, Today, Timescale, and Task Progress. However, as a workaround you could concatenate the task Duration to the task Name, something like this:

    John

  • John-project's avatar
    John-project
    Silver Contributor

    henrikstrand,

    Sorry but the timeline text is limited to 4 items: Task Dates, Today, Timescale, and Task Progress. However, as a workaround you could concatenate the task Duration to the task Name, something like this:

    John

Resources