Forum Discussion

Dive1082's avatar
Dive1082
Copper Contributor
Jun 21, 2022
Solved

Timeline showing 1 year later

Hi all, I have created a program tracker Gannt chart with a timeline running along the top. I have set the start dates and finish dates as 01/04/22 - 31/03/25. When I look at the timeline, it has the...
  • Dive1082's avatar
    Jun 21, 2022
    Its ok, I worked it out. For anyone else with a similar query, you click "file">"options">"Schedule"check the box that says "Use starting year for FY numbering" then click ok

Resources