Forum Discussion
NSocci
May 04, 2022Copper Contributor
Time Sheets
We have implemented the Time Sheet feature of PWA to track actual time spent on projects. We would like to decouple actual time entered from changing either timelines or percentage complete. Is th...
Paul_Mather
May 04, 2022MVP
Hello NSocci ,
Do you have the "Single Entry Mode" option set on the "Timesheet Settings and Defaults" page? If so, Uncheck that, that way the updates from the Timesheet do not create Task Status updates.
Paul