Time Sheets - PWA - Custom Enterprise column not displaying

Hello,  I'm hoping someone can help, I have set up a custom text field with data that I want to use and display in the Time Sheet view of PWA for a selection of users as I need to be able to report ...
  • LisaGaillard's avatar
    Jun 03, 2022
    I figured out the issue by myself for anyone who is interested or comes back here in the future, the custom field only populated to certain users timesheets as I had created the custom field after creating the timesheet reporting peroid for the month of May. The custom field now automatically shows in all new timesheet reporting peroids, june, july etc. (created after the custom entreprise field was added)

    and of course it shows up in the Odata to be used by PowerBI or other data modelization methods.