Forum Discussion
CharlesB1325
Aug 07, 2024Copper Contributor
Time Reporting to Project Not Task
Hi All, My organization has struggled to implement MS Project Timesheets in the past due to the amount of work and coordination needed to manage time reporting at the task level. Frequently, reso...
- Aug 07, 2024
Given the amount of trouble you have had with Timesheet reporting PWA, I am surprised you have not abandoned this entirely. However, if you do want to continue having team members to report high-level progress, there are two settings on the Timesheet Settings and Default page in PWA that your app admin will need to change. I have highlighted them with the red outlines in the image below. Hope this helps.
RodFromm
Aug 12, 2024Steel Contributor
CharlesB1325 Were a pretty large organization and we had the same issues. To get around this, we created two WBSs. One for timesheet reporting tasks and another for managing the project schedule.
CharlesB1325
Aug 12, 2024Copper Contributor
Very interesting! Thank you. Do you open a separate WBS for each project, or have people report time for multiple projects into the same WBS?