Time Reporting to Project Not Task

Hi All,   My organization has struggled to implement MS Project Timesheets in the past due to the amount of work and coordination needed to manage time reporting at the task level. Frequently, reso...
  • Dale_HowardMVP's avatar
    Aug 07, 2024

    CharlesB1325 

    Given the amount of trouble you have had with Timesheet reporting PWA, I am surprised you have not abandoned this entirely. However, if you do want to continue having team members to report high-level progress, there are two settings on the Timesheet Settings and Default page in PWA that your app admin will need to change. I have highlighted them with the red outlines in the image below.  Hope this helps.

     

     