Forum Discussion
Time Reporting to Project Not Task
- Aug 07, 2024
Given the amount of trouble you have had with Timesheet reporting PWA, I am surprised you have not abandoned this entirely. However, if you do want to continue having team members to report high-level progress, there are two settings on the Timesheet Settings and Default page in PWA that your app admin will need to change. I have highlighted them with the red outlines in the image below. Hope this helps.
Thank you very much for your time and response! I have updated our PWA to enable top-level time reporting, however through my testing it seems that the resource must still add a task from the project to their timesheet for the summary row to appear.
I have not tried switching the default from task assignments to current projects for fear of the repercussions. I have not been able to find any guidance as to what will happen to the existing timesheets if I change this selection. Do you know if it will remove all of the tasks that resources have already added to their timesheets? Can it be undone?
I learned a valuable lesson when I changed the permissions mode in the PWA before thoroughly understanding the impact ![]()
Truth be known, you are venturing into "uncharted territory" with your intended use of the Timesheet functionality in PWA. All of my clients either use the Timesheet feature to capture daily time on a task by task basis, or they don't use it at all. So, I am not sure I can answer your questions. My assumption, however, is that existing timesheets would not be impacted, as the changes you make (you would need to make BOTH changes), would only impact future timesheets. That's about the best I can do for you.
However, if there is anyone in this user group that has ideas for you, I would gladly solicit their ideas. Sorry, but hope this helps.