This project contains links to one or more data sources
Every time I open this project I get this message. have tried everything google suggested, but it isn't a common issue with project, but it is on excel. Additionally, the project is about twice the s...
- Nov 09, 2021
Apparently at some point you or someone else created imbedded links to the Project file. It could have been a hyperlink, the file was part of a master/subproject structure, a resource pool/sharer structure, or had cross-project links to another file, or perhaps had an imbedded image. Lots of possibilities.
Also, the fact that your file is also much larger than your other similar files indicates there may be corruption. I suggest you try each of the methods in the following Wiki article.
John
David1979
Mar 27, 2022Copper Contributor
Hi John
Every time I open an MS P file, I get the following error. This does not happen when my colleague tries to open the same files:
"This project contain slinks to one or more data sources that may be unsafe or have been disabled ...."
Every time I open an MS P file, I get the following error. This does not happen when my colleague tries to open the same files:
"This project contain slinks to one or more data sources that may be unsafe or have been disabled ...."
John-project
Mar 28, 2022Silver Contributor
David1979,
That's not much information to go on.
1. Where are the files stored?
2. Do the files have any hyperlinks?
3. Do the files have external predecessors/successors?
4. Are the files part of a linked structure (i.e. master/subproject or resource pool/sharer file)?
5. What version of Project do you have and what version does your colleague have?
6. Did you try the methods listed in the Wiki article I mentioned in my original response on this thread?
John
That's not much information to go on.
1. Where are the files stored?
2. Do the files have any hyperlinks?
3. Do the files have external predecessors/successors?
4. Are the files part of a linked structure (i.e. master/subproject or resource pool/sharer file)?
5. What version of Project do you have and what version does your colleague have?
6. Did you try the methods listed in the Wiki article I mentioned in my original response on this thread?
John