Forum Discussion

SaraFennah's avatar
Nov 01, 2016
Solved

Team Resource Pool Capacity

Working in Project Online,  I have a customer who wants to use Resource Teams, but tasks assigned to Team Resource Pool Resource do not appear to show in the Capacity Planning graphs, though they do ...
  • TrebGatte's avatar
    TrebGatte
    Jan 20, 2017

    We've reported this as an issue as they used to appear in the Resource charts. In the interim, we've built dashboards in Power BI that automatically include this information. So, you may have to address this using reporting in the interim.

     

    Treb Gatte, Project MVP, https://tumbleroad.com