Forum Discussion
BlissL
Jun 14, 2022Brass Contributor
Tasks not showing on PWA Project SharePoint Site?
Hi again, I have a project that's published to the PWA and have connected a SharePoint site to the project. However on the SharePoint site when I click on tasks it shows nothing, only a message say...
- Jun 14, 2022
Hello BlissL ,
If you want to see the Tasks synchronised to the Project site from PWA, you need to see the option on the Enterprise Project Type:
- PWA Settings
- Enterprise Project Types - EPT
- Select the EPT
- Scroll down to the Synchronization section
- Check the option for "Sync SharePoint Tasks Lists"
- Save
- Repeat for other EPTs as needed
Next time you publish the project/s the tasks for that project that was published will sync to the Project Site.
Paul
Paul_Mather
Jun 14, 2022MVP
Hello BlissL ,
If you want to see the Tasks synchronised to the Project site from PWA, you need to see the option on the Enterprise Project Type:
- PWA Settings
- Enterprise Project Types - EPT
- Select the EPT
- Scroll down to the Synchronization section
- Check the option for "Sync SharePoint Tasks Lists"
- Save
- Repeat for other EPTs as needed
Next time you publish the project/s the tasks for that project that was published will sync to the Project Site.
Paul