"Tasks by Planner" and "Microsoft Project for the Web"

Thank you for your time,   1) I can use a Webpart on SharePoint to display information from "Tasks by Planner", but I cannot do the same for "Planner". Is "Tasks by Planner" the new Planner?   2)...
  • RodFromm's avatar
    Feb 26, 2024

    Leonel GUZMAN The integration of Planner and Project for the Web (default environment only) can be rather confusing.  Here is a lengthy post that may help The new Microsoft Planner: A unified experience bringing together to-dos, tasks, plans and projects - Page 8 - Microsoft Community Hub


    Hopefully this will help alleviate some of the confusion.

    • Currently the Tasks by Planner and To Do app, creates a Planner project without the Timeline functionality.
    • Currently the Project app creates a Project for the Web project in the default environment, or you can link it to a project in a named environment.
    • Currently in the Planner app, you can convert a copy of a Planner to a Project for the Web project in the default environment.
    • At this time I do not believe it's possible to embed a Project for the Web project in a SharePoint site.