Forum Discussion
SeanW123
Nov 16, 2023Copper Contributor
Task/Project Duration not Calculating
Hello, I have a detailed plan using Microsoft project where I have created all my tasks, inputted their predecessors, estimated the amount of work required and assigned resources. All I need now is f...
Nov 16, 2023
Also, I forgot to mention that if you want to see the total Duration for the entire project, you need to display the Project Summary Task (aka Row 0 or Task 0). To do this, click the Format tab (it may be labeled Gantt Chart Format) to display the Format ribbon. At the far right end of the ribbon, select the Project Summary Task checkbox. The Project Summary Task will show you the Duration of the entire project. Hope this additional information helps.