Task/Project Duration not Calculating
Hello, I have a detailed plan using Microsoft project where I have created all my tasks, inputted their predecessors, estimated the amount of work required and assigned resources. All I need now is f...
Nov 16, 2023
SeanW123 --
I see two major problems in the project shown in your screenshot. BTW, thanks for sharing that screenshot; it really helps with troubleshooting your issue. Your first problem is that you have assigned a Task Calendar to every task in your project. This is totally unnecessary and I strongly advise that you remove the Task Calendar from every task. Your second problem is that the tasks in the Mechanical Completion are set to Manually Scheduled. Change them to Auto Scheduled. If you make these two sets of changes to your problem, this will probably resolve the problem you are describing. Hope this helps.
I see two major problems in the project shown in your screenshot. BTW, thanks for sharing that screenshot; it really helps with troubleshooting your issue. Your first problem is that you have assigned a Task Calendar to every task in your project. This is totally unnecessary and I strongly advise that you remove the Task Calendar from every task. Your second problem is that the tasks in the Mechanical Completion are set to Manually Scheduled. Change them to Auto Scheduled. If you make these two sets of changes to your problem, this will probably resolve the problem you are describing. Hope this helps.
- SeanW123Nov 21, 2023Copper ContributorThis one helped