Forum Discussion
Woody
Aug 10, 2023Copper Contributor
Task synchronization to Project Site - Only 5 columns in Gantt-Chart view
Hi!
While tasks from the Project Plan are perfectly synced to the Project Site we are lacking some useful columns in the Gantt Chart view. Only 5 columns with project data are synced to the Tasks list in the Project Site:
Title, Start Date, Due Date, % Complete, Predecessors and Assigned To:
Is there any way we can have other Enterprise Custom Fields in this view automatically synced when the Project Plan is published?
For instance, Notes column or other ECFs, it would be really helpful.
Thank you in advance!
1 Reply
Sort By
- JGrantTylerCopper ContributorWoody did you ever find a solution for this? I am trying to do the same thing.