Task summary and sub task duratiom
If I input the sub-task duration in hours;min & also in obtions the in duration has been set to hours. But client wants summary tasks to be in days. So if I change the obtions back to days after com...
JeanineB007
Apr 15, 2024Copper Contributor
JeanineB007
Apr 15, 2024Copper Contributor
I only work with 3 calendars.
1. Hi-teck (STD) Mon-Fri - 08:00-17:00 (8hr / 40hr,week) * All planning and procurement. (Summaries 1-4)
2. Mondi-24hr (mon-sun) 00:00- 00:00 (summary 5 - 6.3)
3. Mondi
1. Hi-teck (STD) Mon-Fri - 08:00-17:00 (8hr / 40hr,week) * All planning and procurement. (Summaries 1-4)
2. Mondi-24hr (mon-sun) 00:00- 00:00 (summary 5 - 6.3)
3. Mondi
- John-projectApr 15, 2024Silver ContributorJeanineB007,
It will be easier to help you if you send me your file along with a thorough explanation of exactly what you need. You can contact me at the address below. I will ask some questions.
John
jmacprojataticlouddotdotcom
(remove obvious redundancies)