Task Start and Finish dates not in synch with Assignments view
- Sep 11, 2024
PaulaH95 --
I duplicated the steps you exactly as you described them, and following is what I see. The Start date of the task as 09/16/24 is correct, since that is the date on which you entered 0h of work. If you Zoom the Assignments view to the Daily level, you will note that there are blank entries for each of the work days during the week of September 15; however, those dates actually contain 0h for each day, even though the zeroes are not displayed. This means that the Start date of the task is 09/16/24.
Also, during the following two weeks, Project for the Web timephased the work hours as .8h per day for each work day. This means that the Finish date of 10/04/24 is also correct. So, what I see in Project for the Web is CORRECT in both the Grid view and the Assignments view.
My question for you is why you followed this totally convoluted process of timephasing the work on the task. If the work does not start until 09/23/24, why didn't you enter that date in the Start field for the task? So, based on what I see in your project and my experimental project, the Start dates and Finish dates ARE correct. Hope this helps.
which version of MS project are you using ? are you using manual scheduling for the tasks, what is the task type also can you confirm the view you are using, i tried to perform the same actions using the resource usage view and the dates did move to cover the dates of the work