Task should not be started on weekend but can run continuously during weekend

I have several tasks that takes 18 to 25 days in row. Those tasks should be started from Monday to Friday. I could not made a schedule for those tasks
  • John-project's avatar
    John-project
    Dec 14, 2023

    Dale_HowardMVP,

    Or......how about this "end around run"? As soon as the "milestone" takes on a non-zero value, the Monday through Thursday only custom calendar as the Task Calendar does the trick.

    John 🙂