Forum Discussion
Shahram
Dec 12, 2023Copper Contributor
Task should not be started on weekend but can run continuously during weekend
I have several tasks that takes 18 to 25 days in row. Those tasks should be started from Monday to Friday. I could not made a schedule for those tasks
- Dec 14, 2023
Or......how about this "end around run"? As soon as the "milestone" takes on a non-zero value, the Monday through Thursday only custom calendar as the Task Calendar does the trick.
John 🙂