Forum Discussion
Shahram
Dec 12, 2023Tin Contributor
Task should not be started on weekend but can run continuously during weekend
I have several tasks that takes 18 to 25 days in row. Those tasks should be started from Monday to Friday. I could not made a schedule for those tasks
- Dec 14, 2023
Or......how about this "end around run"? As soon as the "milestone" takes on a non-zero value, the Monday through Thursday only custom calendar as the Task Calendar does the trick.
John 🙂
Dec 13, 2023
Ignacio --
I hereby give you the "I Corrected Dale Howard MVP" award for catching my erroneous response to this question. I thank you for correcting my mistake. You are indeed correct that the Task Calendar has NO EFFECT on milestone tasks. Well done, my friend! I think the user should refer to your post about breaking up the task in question. Hope this helps.
I hereby give you the "I Corrected Dale Howard MVP" award for catching my erroneous response to this question. I thank you for correcting my mistake. You are indeed correct that the Task Calendar has NO EFFECT on milestone tasks. Well done, my friend! I think the user should refer to your post about breaking up the task in question. Hope this helps.
John-project
Dec 14, 2023Silver Contributor
Or......how about this "end around run"? As soon as the "milestone" takes on a non-zero value, the Monday through Thursday only custom calendar as the Task Calendar does the trick.
John 🙂
- ShahramDec 15, 2023Tin ContributorGreat. Thank you very much. It works.
- John-projectDec 14, 2023Silver ContributorDale,
My take is a milestone should not be called task, just like a summary is are not task. Unfortunately I see many users, mostly newbies, who don't quite understand this. So I threw in the 1 minute duration "milestone" to create a true task and then your approach works fine.
Although I can see the advantage of having calendar control over a milestone, (present case in point), I can also see some logic in not having milestones responsive to calendars.
It's interesting, I haven't seen any feedback from the original poster. Maybe we confused him and now he's not sure what to do.
John - Dec 14, 2023John -- It makes no sense that a Task Calendar will not override the schedule of a milestone task. But if memory serves me correctly, this has been the default behavior of Microsoft Project for a long time, which Ignacio reminded me about. I would call this sloppy design, but it is what it is. 😞