Task should not be started on weekend but can run continuously during weekend
I have several tasks that takes 18 to 25 days in row. Those tasks should be started from Monday to Friday. I could not made a schedule for those tasks
- Dec 14, 2023
Or......how about this "end around run"? As soon as the "milestone" takes on a non-zero value, the Monday through Thursday only custom calendar as the Task Calendar does the trick.
John 🙂
John-project
Dec 13, 2023Silver Contributor
Ignacio Martin,
Yes, you are correct, I didn't test out my approach before posting. The approach you suggest will of course work but I think a more robust solution is with a macro.
John
Yes, you are correct, I didn't test out my approach before posting. The approach you suggest will of course work but I think a more robust solution is with a macro.
John
Dec 13, 2023
John --
In response to Martin's reply, I DO think that using a milestone would be a workable solution. However, the milestone would need a custom calendar applied to it that only schedules work to take place from Monday through Thursday only, but not on a Friday. This would allow the successor task to start from Monday through Friday, but NOT on a Saturday or Sunday. Your solution was so close! Just a thought. Hope this helps.
In response to Martin's reply, I DO think that using a milestone would be a workable solution. However, the milestone would need a custom calendar applied to it that only schedules work to take place from Monday through Thursday only, but not on a Friday. This would allow the successor task to start from Monday through Friday, but NOT on a Saturday or Sunday. Your solution was so close! Just a thought. Hope this helps.
- John-projectDec 13, 2023Silver Contributor
- Dec 13, 2023John--
This is just another example of how people like you and me "team up" to help people with their Microsoft Project questions. 🙂- Ignacio_MartinDec 13, 2023Steel ContributorHi
If I'm not mistaken, the problem is that the milestone is not affected by calendars as it has a duration of 0 days.
In other words, I think it is not reprogrammed and is not a solution.
Please join me too, if only for this opportunity.
Regards
Ignacio MartÃn