Forum Discussion

ajaffke's avatar
ajaffke
Copper Contributor
Feb 10, 2022
Solved

Task setting that doesn't affect overall project

Is there a way to add a task to your project that doesn't automatically affect the overall project calculation? For example, I have a task where I need to track if someone ordered a sign. If that per...
  • John-project's avatar
    Feb 10, 2022
    ajaffke,
    First of all, if your plan will continue whether or not the sign was ordered, I question whether the sign "task" should even be in the schedule.

    However if you still want to show the sign task don't have any other tasks in your plan dependent on it (i.e. no predecessors or successors). In my view this is bad practice but it does address your scenario.
    John

Resources